1. NATIONAL COLLEGE „ALEXANDRU PAPIU ILARIAN”
1. PROJECT’S PRESENTATION
The project’s general objective is the improvement of education infrastructure’s quality and the endowment of the schools in
The project’s specific objectives aim the maintenance and the improvement of
- Improving infrastructure’s quality of the
- Increasing the quality of endowments of the National College “ Papiu Ilarian”- Tirgu- Mures, until February, 2012;
The rehabilitation and modernization of the
The accomplishment of the specific objectives will lead to the maintenance of the actual number of students at the
Also, by achieving these objectives, it will be also accomplished the specific objective of the Priority Axis 3- “Improvement of the social infrastructure”, key area of intervention 3.4- “Rehabilitation, modernization, development and equipping of pre-university, university education and continuous vocational training infrastructure”, through:
- Improvement of education infrastructure
The project will rehabilitate and modernize an important school unit, The National College “Papiu Ilarian”-
Due to the rehabilitation and modernization of the College, the number of students will maintain, and the school abandon’ rate will be the same, meaning 0%.2. PROJECT’S VALUE:
The total value of the project is de: 12.651.795,69 lei from which:
Non-reimbursable financial assistance: 10.257.180,86 lei
Co- financing: 374.580,22 lei
The difference of 2.020.034,61 lei is represented by the VAT of the project’s total value.
3. FINANCING SOURCE: REGIONAL OPERATIONAL PROGRAMME 2007 – 2013, PRIORITY AXIS 3. “Improvement of the social infrastructure”, KEY AREA OF INTERVENTION 3.4 “Rehabilitation, modernization, development and equipping of pre-university, university education and continuous vocational training infrastructure”
Management Authority for Regional Operational Programme: MINISTRY OF REGIONAL DEVELOPMENT AND TOURISM
4. IMPLEMENTATION PERIOD: 16 months after signing the contract
5. IMPLEMENTATION RESPONSIBLE: THE SERVICE OF INTERNATIONAL FINANCING PROJECTS IN COLLABORATION WITH SCHOOLS DIRECTION
6. STAGE: - evaluation
2. SCHOOL „GHEORGHE ŞINCAI”
The project’s general objective is the improvement of education infrastructure’s quality and the endowment of the schools in
The project’s specific objectives aim the improvement of School “Gheorghe Sincai” infrastructure, through its rehabilitation and modernization. Thus, the specific objectives are:
- Improving infrastructure’s quality of the School “Gheorghe Sincai” Tirgu Mures, until the end of January, 2012;
- Increasing the quality of endowments of the School “Gheorghe Sincai” Tirgu Mures, until the end of January, 2012;
The rehabilitation and modernization of the school refers to thermal rehabilitation of the building, but also to the acquisition of endowments and technical equipments for laboratories and cabinets.
The accomplishment of the specific objectives will lead to the maintenance of the actual number of students at the School “Gheorghe Sincai” - Tirgu Mures, by offering an educational process at European standards.
Also, by achieving these objectives, it will be also accomplished the specific objective of the Priority Axis 3- “Improvement of the social infrastructure”, key area of intervention 3.4- “Rehabilitation, modernization, development and equipping of pre-university, university education and continuous vocational training infrastructure”, through:
- Improvement of education infrastructure
The project will rehabilitate and modernize an important school unit, School “Gheorghe Sincai” - Tirgu Mures. This is a vocational school (mechanics), formed and structured in high school, post high school and evening classes, all which are intended to serve social and cultural needs of the inhabitants of this city.
The School Gheorghe Şincai, built in 1976, has three different wings, as follows:
- Wing A – the main body, the school itself- divided into 3 levels: the ground-floor +2 levels
- Wing B – Gym and workshops – divided into 2 levels: the ground-floor +1 level
- Wing C – Workshops - divided into 2 levels: the ground-floor +1 level
Due to the rehabilitation and modernization of the College, the number of students will maintain, and the school abandon’ rate will decrease or even disappear. (presently, the school abandon’ rate is 1,8%).
2. PROJECT’S VALUE:
The total value of the project is de: 9.551.084,01 lei from which:
Non-reimbursable financial assistance: 7.862.168,60 lei
Co- financing: 163.952,42 lei
The difference of 1.524.962,99 lei is represented by the VAT of the project’s total value.
3. FINANCING SOURCE: REGIONAL OPERATIONAL PROGRAMME 2007 – 2013, PRIORITY AXIS 3. “Improvement of the social infrastructure”, KEY AREA OF INTERVENTION 3.4 “Rehabilitation, modernization, development and equipping of pre-university, university education and continuous vocational training infrastructure”
Management Authority for Regional Operational Programme: MINISTRY OF REGIONAL DEVELOPMENT AND TOURISM
4. IMPLEMENTATION PERIOD: 15 months after signing the contract
5. IMPLEMENTATION RESPONSIBLE: THE SERVICE OF INTERNATIONAL FINANCING PROJECTS IN COLLABORATION WITH SCHOOLS DIRECTION
6. STAGE: - evaluation
3. „
The project’s general objective is the improvement of education infrastructure’s quality and the endowment of the schools in
The specific objectives refer to the improvement and infrastructure extension of the Dacia Gymnasium Wings, A and B, from Tirgu Mures, through rehabilitation, modernization and mansard- roofing. Thus, the specific objectives are:
- Improving infrastructure’s quality of the Dacia Gymnasium, Wing A, Tirgu Mures, until March, 2012;
- Improving infrastructure’s quality of the Dacia Gymnasium, Wing B, Tirgu Mures, until March, 2012;
- The extension of Dacia Gymnasium, Wing A, Tirgu Mures, until March, 2012;
- The extension of Dacia Gymnasium, Wing B, Tirgu Mures, until March, 2012;
- Increasing the quality of endowments of the Dacia Gymnasium, Wing A, Tirgu Mures, until March, 2012;
- Increasing the quality of endowments of the Dacia Gymnasium, Wing B, Tirgu Mures, until March, 2012;
The rehabilitation and modernization of the Dacia Gymnasium’ buildings, wing A and B, refers to the renovation of the buildings, but also to the acquisition of endowments, technical equipments for laboratories and cabinets and IT equipments.
The extension of Wing A and B refers to mansard- roofing, in order to grow the Gymnasium’s capacity.
The accomplishment of the specific objectives will lead to the growth of the number of students at the Dacia Gymnasium” - Tirgu Mures, by extension of the two buildings and by offering an educational process at European standards.
Also, by achieving these objectives, it will be also accomplished the specific objective of the Priority Axis 3- “Improvement of the social infrastructure”, key area of intervention 3.4- “Rehabilitation, modernization, development and equipping of pre-university, university education and continuous vocational training infrastructure”, through:
- Improvement of education infrastructure
The project will rehabilitate and modernize an important school unit, Dacia Gymnasium - Tirgu Mures. This school has 2 wings: wing A, where students from primary school have their classes, and wing B- the gymnasium.
Due to the extension of the Dacia Gymnasium, the number of students will grow, and the school abandon’ rate will be the same, meaning 0%.
It is aimed that at the end of the project’s implementation (March 2012), due to the new classrooms resulted from the vertical extension (mansard- roofing), the number of students will grow as follows:
- Dacia Gymnasium, Wing A – 523 students and pre-school children, instead of 505
- Dacia Gymnasium, Wing B – 327 students and pre-school children, instead of 304
2. PROJECT’S VALUE:
The total value of the project is de: 11.307.445,21 lei from which:
Non-reimbursable financial assistance: 8.826.100,30 lei
Co- financing 675.954,50 lei
The difference of 1.805.390,41 lei is represented by the VAT of the project’s total value.
3. FINANCING SOURCE: REGIONAL OPERATIONAL PROGRAMME 2007 – 2013, PRIORITY AXIS 3. “Improvement of the social infrastructure”, KEY AREA OF INTERVENTION 3.4 “Rehabilitation, modernization, development and equipping of pre-university, university education and continuous vocational training infrastructure”
Management Authority for Regional Operational Programme: MINISTRY OF REGIONAL DEVELOPMENT AND TOURISM
4. IMPLEMENTATION PERIOD: 17 months after signing the contract
5. IMPLEMENTATION RESPONSIBLE: THE SERVICE OF INTERNATIONAL FINANCING PROJECTS IN COLLABORATION WITH SCHOOLS DIRECTION
6. STAGE: - evaluation